Topic 1 Question 168
2 つ選択A company has a hybrid IT setup that includes services that run in an on-premises data center and in the AWS Cloud. The company is using AWS Direct Connect to connect its data center to AWS. The company is using one AWS Site-to-Site VPN connection as backup and requires a backup connectivity option to always be present. The company is transitioning to IPv6 by implementing dual-stack architectures.
Which combination of steps will transition the data center's connectivity to AWS in the LEAST amount of time?
Create a new Site-to-Site VPN tunnel for the IPv6 traffic.
Create a new dual-stack Site-to-Site VPN connection between the data center and AWS. Provision routing. Delete the original Site-to-Site VPN connection.
Associate a new dual-stack public VIF with the Direct Connect connection. Migrate the Direct Connect traffic to the new VIF.
Add a new IPv6 peer in the existing VIF. Use the IPv6 address provided by Amazon on the peer router.
Send IPv6 traffic between the data center and AWS in a tunnel inside the existing IPv4 tunnels.
ユーザの投票
コメント(10)
AD are correct since a new vpn is needed and a new IPv6 peer can be added to the existing vif BE are wrong - since you cannot add iPv6 to an existing s2s and a s2s cannot be dual stack
(https://docs.aws.amazon.com/vpn/latest/s2svpn/ipv4-ipv6.html) C is good but not fulfil the least amount of time requirement👍 5tromyunpak2024/03/26A and E
👍 3jinu2024/03/19- 正解だと思う選択肢: AD
A D is correct.
👍 3cerifyme852024/04/14
シャッフルモード